IAR Submission
(This guide is prepared for the purpose of the CIHI 2015-2016 specifications)
Also See attachment
Navigate to e-Assessment > Submission > IAR Submission
- Select the Submission type CCRS IAR
- Select the submission period/quarter (any pending IAR assessments in Q1-2015)
- Click on ‘Select All’ in order to select all assessment for the period.
- Click on ‘Review’ to start the process
- Click ‘Continue’ to proceed with the process
- Click on ‘Send to IAR’; this action submits the file electronically from Mede-care to CCIM
Note: When the IAR Submission gets to CCIM, it should generate a ‘Transaction ID’ under the ‘IAR History’ tab for the submitted quarter.